Prairie Lithium has produced its first surface brine from a production well at Pad #1 as part of its project in Saskatchewan, Canada.

This follows the completion of a well re-entry, perforation, and swabbing programme designed to access production zones within the Duperow Formation.

Discover B2B Marketing That Performs

Combine business intelligence and editorial excellence to reach engaged professionals across 36 leading media platforms.

Find out more

The recent activities include the expansion, contouring, and grading of the working area at Pad #1 to accommodate additional infrastructure required for the company’s phase 1 development.

According to Prairie Lithium, these works build on previously installed production and disposal wells, supporting power infrastructure, and the delivery of a commercial-scale four-column direct lithium extraction (DLE) unit.

The initial brine production meets a milestone set out for the fourth quarter (Q4) of 2026.

Brine recovered from the well will be used for continued metallurgical testing, which Prairie Lithium said forms part of its ongoing development priorities.

Funding for the project’s phase 1 development is supported by C$6.3m in interest-free financing from the Canadian government through Prairies Economic Development Canada.

The funding is intended to assist with procurement and installation of the phase 1 processing equipment and other necessary plant systems.

Prairie Lithium’s next steps involve ongoing metallurgical testing using the recovered brine from Pad #1.

The company is also preparing to install additional site infrastructure and planning for processing equipment and lithium chloride concentration systems.

Site initiatives at Pad #1 are described as indicators of progress towards its intended phase 1 development, set against the backdrop of current market conditions.

Prairie Lithium executive chairman Paul Lloyd said: “Successfully bringing brine to the surface from our production well is an important operational milestone for Prairie lithium.

“Completing the site expansion, civil works and re-entry programme ahead of the Canadian winter is another positive step in preparing Pad #1 for the next stages of development.

“The recovered brine will now be used for continued metallurgical testing as we advance our phase 1 plans.”