PDI Gold has received exploitation permits from the Government of Guinea for its Bankan Project and Mansounia deposit, clearing the way for the company to begin construction and mining operations at both gold sites.

The permits are the final regulatory approvals needed for the Bankan Project and for mining to commence at Mansounia within the broader Kiniéro Gold Mine.

Discover B2B Marketing That Performs

Combine business intelligence and editorial excellence to reach engaged professionals across 36 leading media platforms.

Find out more

According to PDI Gold, the Bankan exploitation permit is held by the company’s subsidiary Hamana Gold SA and covers 98.6km² with an initial 15-year term.

The Mansounia permits, issued to Sycamore Mine Guinee SAU, cover a total area of 71.2km² and also run for 15 years.

Under Guinea’s mining code, the Government holds a 15% ownership stake in each of the permits.

A definitive feasibility study (DFS) for Bankan was completed in June 2025, projecting annual gold production of about 250,000oz for 12 years.

The capital cost for the project is estimated at $463m, with all-in sustaining costs of $1,111 per ounce based on a gold price of $3,300 per ounce.

PDI Gold has already made progress on site preparation, engineering, and procurement, including down payments totalling $18m for plant and power infrastructure.

The company expects the first gold pour from Bankan in mid-2028 and said there are ongoing efforts to keep capital costs in line with the initial estimates.

At Mansounia, preparations for mining will begin immediately with the aim of enhancing Kiniéro’s near-term production and cost structure.

Mansounia contains a probable ore reserve of 19.5mt at 0.77g/t gold, representing 0.48moz of gold.

Mine design and grade control drilling have already been completed for the initial stages.

PDI Gold stated that its board has backed an acceleration in engineering, procurement, and compensation activities at Bankan.

Updated schedules and financial projections for Bankan are anticipated by early 2027.

The company’s gold operations in Guinea, including the Kiniéro mine which achieved first gold pour in December 2025, have contributed to local employment and supplier opportunities.

PDI Gold managing director and CEO Matthew Wilcox said: “The grant of the Bankan and Mansounia exploitation permits represents a key milestone for PDI Gold and a major step forward in the development of what we believe is one of West Africa’s most compelling gold districts.”