Blossom Gold has secured approval from the US Bureau of Land Management (BLM) for notices of intent (NoI) to carry out site investigation activities at its RBX claims and the Rosebud West area in Nevada, US.
The company plans to use these areas for primary infrastructure and water supply related to its Rosebud Project.
Discover B2B Marketing That Performs
Combine business intelligence and editorial excellence to reach engaged professionals across 36 leading media platforms.
The RBX claims, located southeast of the core Rosebud claim block, are designated as the site for the project’s main infrastructure.
This includes an ore conveyor, secondary and tertiary crushing, agglomeration and processing facilities, a heap leach pad, and a planned waste rock storage site.
The notices cover work such as access and condemnation drilling, geotechnical test pits, and shallow geotechnical probe holes at these intended facility locations.
At Rosebud West, located southwest of the Rosebud claims, the approved notice allows Blossom Gold to conduct drilling, install groundwater monitoring wells, and undertake test drilling.
This activity is related to an anticipated water requirement of 5,000 acre-feet per year for the project.
Information collected through the geotechnical and groundwater surveys will support the design of project facilities and water-sourcing plans. The findings will inform the company’s feasibility assessment and the preparation of applications for a Federal Plan of Operations and a Nevada Reclamation Permit.
Blossom Gold stated that surface drilling at the Rosebud Project is underway, with underground infill drilling and further metallurgical testing scheduled to begin in December.
Initial results from column testing are also expected that month, with an updated Mineral Resource Estimate targeted for release by the end of the first quarter of 2027.
The company noted that ongoing permitting, preliminary engineering, and geotechnical work under the approved notices of intent will support its planned application for a plan of operations and the initiation of the feasibility process in the second quarter of 2027.
Blossom Gold permitting VP Alan Haslam said: “Collecting site-specific groundwater and geotechnical data on the RBX claims is a critical step on our permitting path.
“Baseline hydrogeology and foundation conditions beneath the planned heap leach pad, waste rock storage and processing facilities are core inputs to the Plan of Operations and Nevada Reclamation Permit application we are preparing for submittal to the BLM Black Rock Field Office and the Nevada Division of Environmental Protection, Bureau of Mining Regulation and Reclamation, as well as to the Environmental Impact Statement and Feasibility Study.”