Projects

Liqhobong Diamond Mine

The Liqhobong diamond mine, located within the Liqhobong valley in the Maluti mountains, approximately 120km east-northeast (ENE) of Maseru, is owned by Liqhobong Mining Development Company (LMDC), a company owned by Firestone Diamonds (75%) and the Kingdom of Lesotho (25%).

Producer of

Diamonds

Location

120km east-northeast of Maseru

Mine Type

Open-pit

Depth

393m

Expand

The Liqhobong diamond mine, located within the Liqhobong valley in the Maluti mountains, approximately 120km east-northeast (ENE) of Maseru, is owned by Liqhobong Mining Development Company (LMDC), a company owned by Firestone Diamonds (75%) and the Kingdom of Lesotho (25%).

The mining lease for Firestone Diamonds is valid until June 2021, with options to renew it by two additional periods of ten years. The project primarily involves the development of an open-pit mine to a depth of 393m and construction of a main treatment plant (MTP).

The definitive feasibility study (DFS) for the project was completed in October 2012 and was revised in November 2013 to increase the estimated cost, due to the inclusion of the grid power infrastructure cost.

Construction was initiated in June 2014 and as of September 2015, 49% of the overall construction works was completed, while the overall engineering design was 90% complete. First production from the project was achieved in 2016. The mine began commercial production in the second quarter of 2017.

Lesotho diamond mine history and geology

The diamond mine was discovered in the 1950s by Colonel Jack Scott. Kopane Diamond Development produced diamond from the satellite pipe between 2005 and 2008. Firestone Diamonds acquired the project in September 2010 and restarted operation from a pilot facility in July 2011, producing more than 325,000ct until October 2013.

The first large-scale evaluation programme on the main pipe was conducted by MineGem (acquired by Kopane in 2001) in the 1990s. The satellite pipe covers a surface area of 1.6ha, while the main pipe, located approximately 300m from the satellite pipe, covers a surface area of 8.6ha.

The diamond mine site integrates four intrusive kimberlite rocks, namely K2, K4, K5 and K6.

Liqhobong mine reserves

The mine is considered to be the world’s third biggest undeveloped kimberlite resource, based on the contained carats. As of September 2015, it was estimated to contain probable reserves of 36.04 million tonnes (Mt) of ore, graded at 26ct / 100t, containing 9.523 million carats (Mct) of diamond.

The combined indicated and inferred resources are estimated to be 83.42Mt, graded at 28ct / 100t, containing 23.08Mct of diamond.

Mining and processing at Liqhobong mine

“The mine is considered to be the world’s third biggest undeveloped kimberlite resource.”

Up to 60% of the total resource will be mined using the open-pit mining method, incorporating three stripping cuts, while the remaining resource is expected to be mined employing either a fourth cut in the open-pit or through an underground operation.

The main treatment plant comprises two 250t an hour trains, which treat 3.6Mt of ore and produce more than 1.1Mct a year of diamond. It integrates a simple scrubbing, screening, crushing and concentration design.

The processing plant incorporates combined jaw and cone crushers, scrubbing and conventional screening, coarse and fines dense medium separation and final concentration using X-ray fluorescence technology.

Infrastructure and construction

“Up to 60% of the total resource will be mined using the open-pit mining method, incorporating three stripping cuts.”

Related major infrastructure at the project site includes a residue storage facility (RSF), a waste rock dump, mine offices and accommodation blocks.

A new 5.8km access road, the power grid connection facilities, earthworks and accommodation facilities were completed as of September 2015. The project also involves the decommissioning and dismantling of the pilot plant at the site.

Financing Firestone Diamonds’ flagship project

The total investment in the project is estimated to reach $185.4m. The project achieved financial closure in May 2014 and is being funded through equity and debt. The strategic investors in the project include the Pacific Road Resource Fund, and the Resource Capital Fund.

An $82.4m debt facility is being provided by the Absa Bank, while the project also benefits from a $30m Eurobond (Series A) debt. The review of the project’s financial model was performed by Operis on behalf of both Firestone Diamonds and Absa.

Contractors involved with the Liqhobong diamond mine

The engineering, procurement and construction management (EPCM) contractor for the project is DPR. The company was also involved in conducting the project’s DFS in collaboration with a number of independent consultants, including Zstar Mining Mineral Resource Consultants, AC Howe, and MPH Consulting, as well as Snowden Mining Industry Consultants, Golder Associates Africa, and Geo Tail.

JB Switchgear has been contracted by DRA to design, manufacture and supply 11 of its Eagle Series motor control centres (MCCs) for the project, while Zest WEG Group’s Generator Set Division manufactured and supplied a containerized three-generator unit with a collapsible snow roof for the project.

Other contractors involved in the project are MGCRST Mining, and Turnkey Civil Group (TCG).

Stefanutti Stocks is responsible for the earth and civil works at the mine.

Related Projects

Bateman Gold Project, Ontario

The Bateman project is an underground gold development in Ontario, Canada. It is 100% owned by Battle North Gold, a…

Horne 5 Project

The Horne 5 is a volcanogenic massive sulphide (VMS) gold-silver-copper-zinc deposit located beneath the former producing Horne gold mine in…