Saracen Mineral has produced the first gold from the A$65m ($46m) Thunderbox gold project in Western Australia (WA).

With the latest development, the company said it is on track to double its production rate to 300,000oz a year.

Saracen said the Thunderbox development has been funded using internal cashflows generated by its Carosue Dam project in WA.

The plant is now fully operational, and commissioning is continuing in order to increase the mine’s design capacity to 2.5Mtpa.

At present, around 210,000t of commissioning ore grading 0.9g/t is stockpiled on the run of mine (ROM) pad.

"Thunderbox gives us the level of production and cashflow sought after by international investors, while enabling us to remain debt-free."

Saracen plans to carry out drilling later in 2016 to extend the project life beyond ten years.

How well do you really know your competitors?

Access the most comprehensive Company Profiles on the market, powered by GlobalData. Save hours of research. Gain competitive edge.

Company Profile – free sample

Thank you!

Your download email will arrive shortly

Not ready to buy yet? Download a free sample

We are confident about the unique quality of our Company Profiles. However, we want you to make the most beneficial decision for your business, so we offer a free sample that you can download by submitting the below form

By GlobalData
Visit our Privacy Policy for more information about our services, how we may use, process and share your personal data, including information of your rights in respect of your personal data and how you can unsubscribe from future marketing communications. Our services are intended for corporate subscribers and you warrant that the email address submitted is your corporate email address.

Saracen managing director Raleigh Finlayson said: "Thunderbox gives us the level of production and cashflow sought after by international investors, while enabling us to remain debt-free.

"The potential plus-ten-year mine life of Thunderbox and the exploration upside at both Thunderbox and Carosue Dam means we have a sustainable production profile with strong growth prospects."

Prior to achieving the production, the company has recently introduced first ore to the grinding circuit and completed refurbishment of all key areas of the processing plant, crushing, grinding and classification, leaching and adsorption.


Image: (Left to right) Saracen non-executive director Martin Reed, chairman Geoff Clifford, processing manager Wayne Heedes and managing director Raleigh Finlayson. Photo: courtesy of: Saracen Mineral Holdings Limited.