Rio Tinto and its partners have been ordered by Guinea Mines Minister Moussa Magassouba to suspend work at the Simandou project, marking a fresh setback in the efforts to develop the long-stalled iron ore project.

This project is being developed by Rio Tinto’s Guinea subsidiary Simfer and the Chinese-supported consortium Winning Consortium Simandou (WCS).

The order from Magassouba came into effect on 4 July 2022.

This decision comes as the project companies failed to extend the deadline to agree on a project joint venture (JV), Reuters reported citing a letter seen by it.

In a letter addressed to the project companies, Magassouba said the firms have shown a ‘lack of willingness’ to work on a partnership.

In a later statement, the government said it is considering talks with new partners in the Simandou iron ore project.

How well do you really know your competitors?

Access the most comprehensive Company Profiles on the market, powered by GlobalData. Save hours of research. Gain competitive edge.

Company Profile – free sample

Thank you!

Your download email will arrive shortly

Not ready to buy yet? Download a free sample

We are confident about the unique quality of our Company Profiles. However, we want you to make the most beneficial decision for your business, so we offer a free sample that you can download by submitting the below form

By GlobalData
Visit our Privacy Policy for more information about our services, how we may use, process and share your personal data, including information of your rights in respect of your personal data and how you can unsubscribe from future marketing communications. Our services are intended for corporate subscribers and you warrant that the email address submitted is your corporate email address.

Magassouba wrote: “Despite the significant concessions the Guinean State has been kind enough to make, it is clear the obstruction is being maintained by both your companies, to the detriment of the interests of the project.”

In March 2022, Guinea’s ruling junta suspended construction work on the Simandou project, seeking clarification on how the mine would preserve national interests.

Subsequently, Rio and WCS signed a framework agreement with the government in the same month, to ‘co-develop’ infrastructure for the mine, including a 670km railway and a port.

On 19 June, the government gave 14 days for the project companies to agree on a JV. The time period itself marks an extension of a previous deadline.

Magassouba said Rio and WCS were stalling over the terms of the government’s interest in the JV.

Through its unit Simfer, Rio Tinto currently owns a 45% stake in Blocks 3 and 4 of the Simandou deposit whereas Chinalco and the Guinean Government respectively hold 40% and 15% stakes.

The SMB Winning Consortium controls Blocks 1 and 2 of the Simandou project.