Minerals 260 has selected NRW Holdings as its preferred mining contractor for the Bullabulling Gold Project, located approximately 65km from Kalgoorlie in Western Australia.

Both companies signed a letter to proceed with early mining services.

Discover B2B Marketing That Performs

Combine business intelligence and editorial excellence to reach engaged professionals across 36 leading media platforms.

Find out more

Under the agreement, NRW will begin procuring equipment, implementing its safety management system and finalising requirements for vehicle workshops ahead of the start of mining.

The Bullabulling Gold Project is an open-pit operation on granted mining leases in the Eastern Goldfields region, 25km south-west of Coolgardie.

According to the JORC 2012 mineral resource estimate, the site contains 190mt at 1 gram per tonne (g/t) of gold, totalling 6.2moz. First gold production is targeted for Q4 2028.

The companies anticipate full mobilisation to the site in the third quarter (Q3) of calendar year 2027, with mining operations projected to begin in the fourth quarter (Q4) of that year.

The initial contract is scheduled to span five years, with an option for extension, and is valued at around A$1bn ($660m) for the first five years.

The contract will be based on a fixed and variable schedule of rates, and the final long-form agreement is expected to be signed after a final investment decision (FID), anticipated in early 2027.

The intended scope of work for NRW under the agreement includes mine site establishment, pre-stripping, dewatering, haul road construction, drilling and blasting, load and haul activities, run-of-mine feed, and grade-control drilling.

Minerals 260 managing director Luke McFadyen said: “We are pleased to be partnering with NRW, who were selected following a highly competitive tendering process.

“The appointment of our preferred mining contractor reflects another important step in the continued de-risking the company is focused on to achieve first gold production in Q4 CY2028 and allows both teams to begin working collaboratively ahead of formal contract execution in early 2027.

“NRW has a long history as a high-quality provider of mining services, and we look forward to a successful partnership with NRW at Bullabulling for many years to come.”

Minerals 260 said that the contract terms align with pre-feasibility study (PFS) assumptions and that staged development and ramp-up will occur over three years, aiming to support a production goal of 7.5 million tonnes per annum (mtpa).

Earlier this month, Minerals 260 secured credit-approved commitments totalling A$410m ($282.6m) to fund the development of its Bullabulling Project.