Tawana Resources and joint venture (JV) partner Alliance Mineral Assets (AMAL) have started commissioning of the Dense Media Separation (DMS) circuit at the Bald Hill lithium-tantalum mine in the Eastern Goldfields of Western Australia (WA).

Bald Hill is a 50:50 JV project between Tawana and AMAL, comprising four mining leases, one mining lease application, 12 exploration licences, eight prospecting licences and one general purpose lease totalling 774km².

Discover B2B Marketing That Performs

Combine business intelligence and editorial excellence to reach engaged professionals across 36 leading media platforms.

Find out more

The Bald Hill project is located 50km south-east of Kambalda in the Eastern Goldfields of Western Australia, and around 75km south-east of the Mt Marion Lithium project.

The JV is targeting first production from the project in the current quarter, with first delivery expected in April.

Tawana noted that the Bald Hill power plant is operational and the motor control centre/low-voltage (MCC/LV) switch room has been commissioned.

“This is a pivotal time for the project, as we make the transition from a developer to producer.”

The JV has also started other activities such as dry commissioning, crushing and stockpiling of ore, while wet commissioning is scheduled to begin on 21 February.

GlobalData Strategic Intelligence

US Tariffs are shifting - will you react or anticipate?

Don’t let policy changes catch you off guard. Stay proactive with real-time data and expert analysis.

By GlobalData

If wet commissioning is successful, the JV expects to start feeding ore to the DMS plant in early March.

Tawana managing director Mark Calderwood said: “We have reached the commissioning stage where construction transforms into operations.

“The plant will be ramped-up to full production run rate over several months; however, we will be producing spodumene concentrates from the day ore is fed to the DMS circuit.

“This is a pivotal time for the project, as we make the transition from a developer to producer.”

Primero Group has designed and developed the Bald Hill DMS and fines tantalum circuit, will operate the plant under an operations and maintenance contract.

The Bald Hill project has an indicated and inferred mineral resource estimate of 18.9 million tonnes (Mt) at 1.18% Li2O and 149ppm Ta2O5 at a 0.5% Li2O cut-off.

Mining Technology Excellence Awards - Nominations Closed

Nominations are now closed for the Mining Technology Excellence Awards. A big thanks to all the organisations that entered – your response has been outstanding, showcasing exceptional innovation, leadership, and impact

Excellence in Action
Recognised with the Research & Development Award , Nokia’s Cognitive Digital Mine uses AI, IoT and digital twin technology to deliver predictive, self-optimising mining operations. Learn how Nokia’s Digital Twin Black Box is enabling safer, more efficient and more profitable mines worldwide.

Discover the Impact