|
In 1955, MIM discovered the Here's Your Chance (HYC) zinc-lead-silver deposit on the McArthur River Station, 900km southeast of Darwin and 100km inland from the Gulf of Carpentaria in Australia's Northern Territory. For 30 years, studies failed to develop a viable production concept, given the costs of building the infrastructure needed. However, in 1989 the company started a prefeasibility study with more cost-effective parameters: selective underground mining and ultra-fine grinding to produce a single zinc-lead concentrate for shipment to its Avonmouth Imperial Smelting Process plant, with government-assisted infrastructure development. The results encouraged MIM and the specially formed consortium, ANT Minerals Pty Ltd, to establish the McArthur River mine (MRM) as a 70:30 joint venture with MIM as the manager. The go-ahead was announced in 1992 and the operations were officially opened September 1995, helping to compensate for declining reserves in the Mount Isa area mines (see separate profiles). ANT Minerals was a consortium of Japanese firms in which Toyoha Mines (a Nikko Kyodo subsidiary) had a 50% interest and Marubeni, Mitsubishi Materials and Mitsui 16.6% each. MIM acquired a further 5% holding during FY2002, while its 75% holding was transferred to Xstrata in 2003 following the companies' merger. MRM now operates within the Xstrata Zinc business unit, Xstata having bought the ANT stake in the project during 2005. In late 2006, Xstrata received government approval for the conversion of McArthur River from underground mining to an open-pit operation. The Northern Territory Government funded about $110m for the open pit development programme. Plans to convert the mine from an underground to an open pit operation were delayed in mid-2008 when the traditional aboriginal land owners opposed the expansion in the courts. Australia’s Northern Territory government responded by hurrying through a new piece of legislation which cleared the way. In its 2007 annual report Xstrata said that the open pit development was going well with the Barney Creek diversion (99% completed) and the McArthur River Rechannelling (95% completed) to be finished in the second quarter of 2008 following the wet season. The Bund Wall was due to be completed in the third quarter of 2008. However, in December 2008 all mining and civil works at MRM were stopped following the judgement of the Federal Court. The decision was based upon procedural errors by the Commonwealth Government. In February 2009, the suspended programme was approved by the Federal Environment Minister on the basis of a few conditions. The conditions included best practice of environmental management and community consultation, and regular studies on freshwater sawfish and migratory birds in the vicinity of the mine. The Northern Territory Government appointed an independent environmental monitor to carry out the mine's environmental monitoring and management programmes. In the second annual assessment of the programme, the monitor indicated that the mine has requisite qualities or resources for the development of an $110m open pit project. The independent monitor also indicated that the mine had conformed to the commitments and conditions required for the open pit project. Geology and reservesThe shallow-dipping stratiform deposit occurs in the HYC Pyritic Shale Member. This package of inter-bedded pyritic siltstone, sedimentary breccia and tuff lies within a belt of sedimentary rocks of Middle Proterozoic age. Seven stacked sulphide orebodies are separated by dolomitic siltstones and sedimentary breccias. Thin tuff bands are common throughout the 55m-thick sequence (average). As of mid-2003, Xstrata stated that McArthur River had proved reserves of 4.6Mt grading 13% zinc, 5.6% lead and 60g/t silver, and 31Mt of probable reserves with 12% Zn, 5.1% Pb and 52g/t Ag. Measured, indicated and inferred resources totalled 124Mt with up to 13% Zn, 6% Pb and 60g/t Ag. The planned change from underground to open-pit mining has led to a recalculation of reserves at the property, with Xstrata quoting open-pit mineable mineral resources as 100Mt grading 12% zinc, 5% lead and 50g/t silver as of mid-2005, plus underground resources of a further 8.3Mt of ore at 14% zinc, 5.6% lead and 58g/t silver. Underground mining"In late 2006, Xstrata received government approval for the conversion of McArthur River from underground mining to an open-pit operation."
Access to the underground mine is provided by two declines, one for personnel and equipment and the other with an ore conveyor from the underground jaw crusher. The zinc-rich high-grade No.2 orebody has been worked first by room-and-pillar mining using a standard drill, blast, muck and ground-support cycle. Low-profile loaders dump into 50t-capacity trucks that make the less-than 800m haul to the crusher. The lower-grade Nos.3 and 4 orebodies allow bulk mining by open stoping and bench mining, with loading on the No.2 level. The change-over to open-pit mining will involve re-equipping the operation. Ore processingUp to four reciprocating plate feeders reclaim crushed ore from the stockpile for SAG milling ahead of flotation. The rougher concentrate is reground to below 10 microns using Xstrata Technology's proprietary IsaMills technology. Cleaner flotation then upgrades the mixed concentrate from 42% to 46% zinc. Test work in 2004 led to flowsheet modifications to increase zinc grade and reduce silica in the concentrate. High-rate thickeners feed Larox pressure filters, which discharge about 360,000t/y of concentrate via conveyors to storage. It is not economic to ship the concentrate to Mount Isa so it is exported. Material is trucked 120km to a purpose-built ship-loading terminal at Bing Bong. Here a barge transfers material from the terminal to bulk ships moored 30km out to sea. One option studied for the conversion to open-pit mining involved the production of zinc at MRM itself, using the group’s direct-leaching Albion Process and, possibly, a 456,000t/y electrowinning and casting facility for SHG zinc and zinc-aluminium alloy. Xstrata is retaining the option to install an Albion refinery at a later date. In January 2007, approval was granted to increase the capacity of the concentrator at McArthur River Mine from annual throughput of 1.8 million tons of ore to 2.5 million tons of ore, for a capital cost of $37 million. It is anticipated that the expanded capacity will be commissioned in the third quarter of 2008. Potential locations for an Albion plant continue to be examined, including the potential for a greenfield smelter on the east coast of Australia or a brownfield expansion at an existing Xstrata Zinc smelter. Production Annual production for 2007 was 1.9Mt ore, 138,000t zinc-in-concentrate. McArthur River Mine continued its open pit development, mining from Stages B, C and transitional ore from Stage D during the year. Stripping began from Stage E in late 2007 to provide a further mining area to support increased production in 2008. A fall in average head grade from 11% in 2006 to 10% in 2007 was due to the mining of transitional ore from the open pit Stages C and D. Mining production increased by 4% year-on-year. Zinc metal production increased by 2%, reflecting a 6% increase in throughput tonnage, partially offset by the treatment of transitional ore stockpiles. Production during 2005 (including six months of Xstrata’s full ownership) was 1.68Mt of ore treated, yielding 154,000 of zinc in concentrate, 4,483t of lead and 1.34Moz of silver. |
![]() Expand ImageNorthern Territory map. |
![]() Expand ImageMcArthur River is located in the Northern Territory outback, halfway between Darwin and Mount Isa. | |
![]() Expand ImageUnderground drilling at McArthur River. | |
![]() Expand ImageA mechanic working in one of the mine's underground workshops. | |
![]() Expand ImageThe enclosed storage facility and barge-loading wharf at Bing Bong, which ships out all of McArthur River's concentrates. |