PJSC Polyus has poured the first doré gold at its Natalka greenfield project as part of the ongoing hot commissioning process at Natalka mill, Russia.

Currently, 24-hour trial runs are in-progress at the processing facility in preparation for commissioning at the Natalka project.

Discover B2B Marketing That Performs

Combine business intelligence and editorial excellence to reach engaged professionals across 36 leading media platforms.

Find out more

The company is planning to ramp-up the capacity of the processing plant, which has an existing capacity of 10mtpa, to ensure the mill delivers annual production of around 420,000oz-470,00oz for the duration of the mine-life.

Through the expansion, Polyus aims to increase overall gold production by around 2.8 million ounces (Moz) in 2019.

“Polyus aims to increase overall gold production by around 2.8 million ounces in 2019.”

The full ramp-up of the Natalka mill is slated for completion by the end of next year.

Natalka is estimated to have a mine life of 31 years of open-pit mining, based on the company’s current life of mine plan .

GlobalData Strategic Intelligence

US Tariffs are shifting - will you react or anticipate?

Don’t let policy changes catch you off guard. Stay proactive with real-time data and expert analysis.

By GlobalData

The project is located in the Tenkinskiy District of the Magadan Region and comprises ore reserves of 16Moz and aggregate mineral resources of 34Moz.

The Natalka deposit was initially discovered in 1942, with pilot mining was carried out in 1944. A processing plant was subsequently built in 1972.

Mining Technology Excellence Awards - The Benefits of Entering

Gain the recognition you deserve! The Mining Technology Excellence Awards celebrate innovation, leadership, and impact. By entering, you showcase your achievements, elevate your industry profile, and position yourself among top leaders driving industry advancements. Don’t miss your chance to stand out—submit your entry today!