Mawson West has completed a feasibility study for the development of a pit cut-back at its Dikulushi copper-silver project in the Democratic Republic of the Congo (DRC).

According to the study, the project has proven and probable mineral reserves of 539kt at 6.1% copper and 182g/t silver, $3.50/lb copper and $30/oz silver.

The process plant has a capacity of 500ktpa and is based on conventional comminution, flotation and filtration processes using a primary jaw crusher, secondary and tertiary cone crushers, ball milling and conventional flotation to produce a copper-silver concentrate.

The pre-strip cost of the project is estimated to be $61m, which will be fully funded from the firm’s existing cash reserves.

Life-of-mine operating costs for the project are expected to be $1.46/lb copper, excluding silver credit and including all mining, processing, general and administrative costs, and product transport and refining costs.

How well do you really know your competitors?

Access the most comprehensive Company Profiles on the market, powered by GlobalData. Save hours of research. Gain competitive edge.

Company Profile – free sample

Thank you!

Your download email will arrive shortly

Not ready to buy yet? Download a free sample

We are confident about the unique quality of our Company Profiles. However, we want you to make the most beneficial decision for your business, so we offer a free sample that you can download by submitting the below form

By GlobalData