Copper Mountain Mining (CMMC) has revised its plan for its British Columbia mine as part of a response to weak copper prices and market uncertainty due to the coronavirus outbreak.

The company has also deferred a $22m capital spend by delaying the installation of the third ball mill at its Copper Mountain mine, until the market condition improves.

Under the revised production guidance, the company expects copper production at the mine to be between 86 and 94 million pounds, down from the previous outlook of between 100 and 113 million pounds.

The company noted that it would delay the mining of higher-grade ore zones in Pit #3 until 2021 when it expects copper prices to recover.

Copper Mountain president and CEO Gil Clausen said: “We are committed to protecting our cash flow and minimising costs given the low and volatile copper price environment that we are currently operating in as a result of the coronavirus impact.

How well do you really know your competitors?

Access the most comprehensive Company Profiles on the market, powered by GlobalData. Save hours of research. Gain competitive edge.

Company Profile – free sample

Thank you!

Your download email will arrive shortly

Not ready to buy yet? Download a free sample

We are confident about the unique quality of our Company Profiles. However, we want you to make the most beneficial decision for your business, so we offer a free sample that you can download by submitting the below form

By GlobalData
Visit our Privacy Policy for more information about our services, how we may use, process and share your personal data, including information of your rights in respect of your personal data and how you can unsubscribe from future marketing communications. Our services are intended for corporate subscribers and you warrant that the email address submitted is your corporate email address.

“We have revised our mine plan to protect and grow cash margin so that we are able to comfortably meet all our obligations, including debt service, while continuing with key projects including the installation of the Direct Flotation Reactors.”

The company has also cut mining rates by over 25% to between 120,000 and 160,000 tonnes per day (tpd) for the remainder of this year, down from around 200,000 tpd, as part of the revised mine plan.

Meanwhile, the death toll from the Wuhan virus has increased to more than 4,200 as of the end of 11 March.

The recoveries have increased to about 65,000, while the total confirmed cases worldwide have passed 119,000.

Italian authorities announced that the cases in Italy have increased to 9,172 with 463 deaths in the country, while recoveries have increased to 724.

To address coronavirus Covid-19, the World Health Organization (WHO) has published research and development (R&D) roadmap.